Broadband SERIOUS Incident Report : ADSL : NEWCASTLE AREA: LOSS OF 8 MUXS : LOSS OF SERVICE : Reference 23606 : Issue 6 :

--------------------------------------------------------------
Incident Manager - Automatic Mailer.
*** PLEASE DO NOT REPLY TO THIS E-MAIL ***
--------------------------------------------------------------

  BT Wholesale - Broadband SERIOUS Incident Report  
     
  Please read the following incident report as it could have an impact on some of your end users  
     
  BT Incident Reference: 23606   Issue : 6  
  Detected Date: 29/09/2009   Detected Time: 08:56  
  Start Date: 29/09/2009   Start Time: 08:47  
  Anticipated Clear Date: 29/09/2009   Anticipated Clear Time: 21:02  
     
  Incident Headline: ADSL : NEWCASTLE AREA: LOSS OF 8 MUXS : LOSS OF SERVICE  
     
  Incident Details: On [29/09/2009], BT experienced some difficulties with 8 MUX's at Newcastle
The fault was identified at 08:47 and and was upgraded within BT to a SI.
The difficulty was as a result of Equipment failure
 
  Progress Details: BT is making progress towards full restoration of Service.
Latest Update:

An Engineer is now on site.
An Engineer is on site carrying out further diagnostics.

Further updates will be provided as soon as possible.

 
  Dialling Codes Affected:
0164201661019122019123019124
019125019127019129019123
 
     

--------------------------------------------------------------
Incident Manager - Automatic Mailer.
*** PLEASE DO NOT REPLY TO THIS E-MAIL ***
System Time Stamp: 29/09/2009 20:11